Rain delay: School construction affected by wet weather

CLINTON - This year’s heavy rains have claimed their latest victim: The new Clinton middle school. Because of rain delays, the construction of the facility slated to open for the 2014-2015 school year is behind schedule.

Eric White with Estes Construction gave members of the Clinton School Board during their Monday meeting an update on the progress of construction. He said the schedule for the project had to be altered, but he didn’t want to put a time frame on how much it had been pushed back at this stage.

“I think what we need to do is once we have a roof on it is look at the options,” White said. “We’re behind, there’s no question about that, where we wanted to be at the time.”  

A groundbreaking for the $21 million project, which is being funded with the one cent sales tax, was held in April. When it opens, sixth-, seventh- and eighth-grade students will attend class in the building, which is being constructed at the corner of 13th Avenue North and 16th Street Northwest.  

The school will have classrooms that facilitate inquiry-based learning and foster education technology and replace Washington Middle School, which was built in 1935, and Lyons Middle School, built in 1971.

White shared the progress that has been made at the site in the last month, such as installing stone columns for the foundation. He said crews are about two days away from having the area that will be underneath the two-story section of the building complete. They have also made progress on the foundation of one of the sections.

Site stormsewer is about wrapped up, White said. They have also made the opening to 13th Avenue North where the entrance to the school will be.  

This month, stone column work and retaining wall work will continue. The first shipment of structural steel for the project will arrive early next month.  

Because of the rain, he explained, the project timeline was changed. In addition to the steps Estes has already implemented because of the revised time schedule, White said his company is looking into stacking trades or overtime work to bring the project back up to speed.  

Board members as well as Superintendent Deb Olson said they often face questions from the public about the new school because of the excitement in the community.

“I think everyone understands we’ve had a wet spring, it’s not your guys’ fault, I don’t know if I speak for everybody here, but I think we’re all getting a little bit nervous,” board member Jack Wenzel said.  

White said he would like to wait until the structure is closed and the roof is up in December before sharing the impact of the weather delays, but assured the board he is aware of where construction is and where it needs to be.

1
Text Only
Local Schools
  • 3-28-14 1B-Signees 1 Four for signing day FULTON, Ill. -- Four seniors from Fulton High School will go on to play college athletics next fall, with all four of them staying within a 3-hour traveling distance. Only Matt Dail, who is going to Trinity Christian College in Illinois to play baske

    March 28, 2014 2 Photos

  • Schools eye same sports-sharing policy CLINTON -- Since 1982 the state of Iowa has allowed athletic sharing agreements between neighboring school districts and it is anticipated that the Clinton School District will continue to take advantage of that allowance into the 2014-2015 school ye

    March 25, 2014

  • 3-25-14 Clinton Middle School photo Projects shuffled as ground thaws CLINTON -- Progress is moving along at the Clinton Middle School, although contractors feel they may be teetering on the edge of their projected schedule. Unfavorable weather and a brutal winter have delayed some aspects of the project, which was ant

    March 25, 2014 2 Photos

  • PTK honorees Students inducted to Phi Theta Kappa CLINTON — The Alpha Theta Beta Chapter of Phi Theta Kappa recently held an induction ceremony for 30 students. Clinton Community College President Karen Vickers, EICC Chancellor Don Doucette and PTK advisors Gina Bielski, Jane Marlowe and Shirley Tur

    March 24, 2014 1 Photo

  • 3-24-14 AP Fulton Fulton eyes AP chemistry course FULTON, Ill. -- Next year, students at Fulton High School could have an opportunity to do something no Fulton Steamer has done before them -- take an advanced placement chemistry course. For the first time in River Bend history, the district is hopin

    March 24, 2014 1 Photo

  • Northeast pushes back technology staffing plan GOOSE LAKE -- The Northeast School District will delay moving forward with a proposal to create a technology position. During the Northeast Board of Education meeting Wednesday night, Superintendent Jim Cox suggested the district wait on transferring

    March 21, 2014

  • Tax rate to remain same GOOSE LAKE -- The Northeast School District has decide not to raise its published tax rate for the upcoming budget year. Business Manager Kristy Weiss presented the 2015 fiscal year budget to the Northeast Board of Education on Wednesday night. The p

    March 21, 2014

  • Schools plan new wrestling room at high school CAMANCHE-- Middle school and junior high school students involved in the Camanche wrestling program currently practice on the Camanche Middle School's stage, sharing space with a variety of other clubs and events. Now, a renovation project is being c

    March 21, 2014

  • Tax levy rate to decline

    Taxpayers in the Camanche School District will see a decrease in their tax rates for the 2014-2015 budget year. The school district is proposing a 62-cent decrease in its tax levy rate. District Business Director and Board of Education Sec

    March 20, 2014

  • Changes in technology use considered

    The Camanche School District is looking at changing how students use technology. As of April 8, Microsoft will stop supporting XP systems, no longer providing automatic fixes, updates and online technical assistance. Camanche Information T

    March 20, 2014

Facebook